Boysun Gas Processing Plant (GPP)

Location

Boysun District, Surkhandarya Region, Uzbekistan

Client

Enter Engineering Pte Ltd - Surhan Gas Chemical Operating Company LLC

Project Overview

The Boysun Gas Processing Plant (GPP) is a cornerstone of Uzbekistan’s energy infrastructure development, aiming to process 5 billion cubic meters (BCM) of natural gas annually from the Mustaqillikning 25 Yilligi field. This field is characterized by high concentrations of CO₂ and H₂S, necessitating advanced treatment technologies.

Scope of Work

  • Engineering, Procurement, and Construction (EPC): Full-cycle EPC services for the gas processing plant and associated infrastructure.
  • Gas Processing Facilities: Design and construction of two processing trains, each with a capacity of 2.5 BCM/year
    • Acid Gas Removal Units (Sulfinol M and Sulfinol X processes)
    • Sulfur Recovery Units
    • Off-Gas Treating Systems
    • Chemical Oxidation of Wastewater